Roadmap¶
The live delivery plan for Cara is the 8-week build — C14–C17 (2026-09-14 → 2026-11-09), tracked straight from each feature's frontmatter and live Linear status so it stays honest as the work moves. Start with the Gantt and the lock dashboard; everything else supports or archives them.
The live plan¶
| View | What it shows |
|---|---|
| Project Timeline (Gantt) | The 8-week plan as a Gantt — a readable by-module roll-up plus the full per-feature chart, shaded by live Linear status. Scrolls horizontally to pan the cycles. |
| Combo Gantt (MS-Project view) | The 8-week plan as a printable MS-Project-style schedule: left task grid (ID · Duration · Start · Finish · PIN) + timeline with finish-to-start dependency arrows (Linear blocked-by solid, provisional overlay dashed), critical path, and per-module summary brackets. Paginates to tabloid. |
| 8-Week Lock Status | Live readiness for C14–C17: features per cycle, lock status, and the open gaps (needs-ticket / needs-design). |
Supporting views¶
| View | What it shows |
|---|---|
| Spec ↔ Linear Coverage (Venn) | Spec-vs-Linear coverage: 33 documented-but-unticketed, 121 ⇄ 129 linked, 136 ticketed-but-undocumented (orphans, decomposed). |
Historical¶
Superseded launch framings and the August-2026 workshop set, kept for context — the plans they describe have been replaced by the live 8-week plan above.
- Executive Summary (Jun–Sep 2026) — the June soft-launch → September rollout framing (its Conor asks, risks, and accounting direction still stand).
- July Pilot → September Rollout — the mid-year two-step launch framing.
- Feature Matrix — the August red / yellow / green scope snapshot (Launch · Aug Wave-1 · Sep Wave · Future).
- Launch Readiness — the 2026-08-04 launch-workshop set: go/no-go checklist, gap register, intake process, and the Conor briefing.
The even earlier insurance-era plan (four phases across nine sprints, the EP01–EP13 epics) is archived in Legacy.